By the end of this chapter you'll be able to…

  • 1Apply the AS 29 decision tree to classify an item as a provision, a contingent liability, or nothing at all, and explain why contingent assets are treated asymmetrically
  • 2Distinguish a legal from a constructive obligation, and both from a mere intention
  • 3Classify a post-employment plan as defined contribution or defined benefit and state the consequence for who bears actuarial and investment risk
  • 4Apply the percentage of completion method under AS 7, including the overriding rule that an expected loss is recognised immediately in full
  • 5Decide when revenue from goods, services, interest, royalties and dividends is recognised under AS 9, and when recognition must be postponed
  • 6Separate adjusting from non-adjusting events after the balance sheet date, and handle proposed dividends correctly
  • 7Apply AS 11 to monetary and non-monetary items, forward contracts, and integral versus non-integral foreign operations
  • 8Present a government grant under each permitted alternative and account for a refund
  • 9Compute deferred tax on timing differences and apply the reasonable certainty and virtual certainty tests to deferred tax assets
💡
Why this chapter matters in CA Intermediate
Three questions are gathered here because their answers share a shape. When does an obligation become something you must record rather than merely mention? When has revenue been earned, as distinct from received? And what do you do when something disturbs figures you already have? AS 29's decision tree in particular is worth learning properly rather than memorising, because its logic recurs across the whole of financial reporting — the same three-step test of present obligation, probable outflow and reliable estimate governs warranty provisions, litigation, restructuring and onerous contracts alike. AS 22 matters for a different reason: it is the standard that makes the tax charge in the accounts correspond to the profit reported beside it.

Liability, Revenue and Impact Standards

Weightage: Chapters 6 to 9 of ICAI's Paper 1 syllabus, together roughly 14 marks. AS 29, AS 7 and AS 22 are the three that produce full questions; the rest produce four and five-mark applications.

Three questions in one chapter

This chapter collects three of ICAI's groups because they are short individually and because their questions share a shape.

Liabilities — AS 15 and AS 29 — ask: when does an obligation become something you must record, as opposed to something you must merely mention?

Revenue — AS 7 and AS 9 — ask: when has the entity earned this, as distinct from when has it been paid?

Items impacting the financial statements — AS 4, 5, 11, 12, 14 and 22 — ask: something has disturbed the figures you already have; what do you do about it?

AS 29 — Provisions, Contingent Liabilities and Contingent Assets

The most heavily examined standard in this chapter, and the one whose logic is worth learning properly because it recurs everywhere.

The three-way split

Everything turns on a single decision tree, and questions almost always want it applied to a fact pattern rather than described.

A provision is a liability that can be measured only by using a substantial degree of estimation. It is recognised when, and only when, all three of the following hold:

  1. the enterprise has a present obligation as a result of a past event;
  2. it is probable that an outflow of resources embodying economic benefits will be required to settle the obligation;
  3. a reliable estimate can be made of the amount.

If a present obligation exists but the outflow is only possible rather than probable, or the amount cannot be measured reliably, it is a contingent liability — disclosed, not recognised.

If there is no present obligation at all, only a possible obligation whose existence will be confirmed by future events not wholly within the enterprise's control, that too is a contingent liability.

If the possibility of an outflow is remote, nothing is done — no recognition and no disclosure.

A contingent asset is never recognised, and is not even disclosed in the financial statements. Where the inflow of economic benefits is virtually certain, the asset is no longer contingent and is recognised.

The asymmetry between contingent liabilities and contingent assets is deliberate and is examined: a possible loss is disclosed, a possible gain is not mentioned at all.

Present obligation

A present obligation may be legal, arising from a contract, legislation or other operation of law, or constructive, arising from an established pattern of past practice, published policies or a sufficiently specific current statement by which the enterprise has created a valid expectation in others that it will discharge those responsibilities.

The distinction that produces most questions is between an obligation and an intention. A board decision to incur expenditure creates no obligation while the board can still change its mind. A published policy of refunding dissatisfied customers, consistently honoured, creates a constructive obligation even though no contract requires it.

Measurement

The amount recognised is the best estimate of the expenditure required to settle the present obligation at the balance sheet date. Where a single obligation is being measured, the individual most likely outcome may be the best estimate. Where a large population of items is involved, the obligation is estimated by weighting all possible outcomes by their associated probabilities — the expected value.

Discounting is not permitted under AS 29 where the effect of the time value of money is material — this differs from the international position and is examined as a point of difference. Gains from expected disposal of assets are not taken into account in measuring a provision.

Reimbursements from a third party are recognised only when it is virtually certain that reimbursement will be received, and are treated as a separate asset, not netted against the provision. The amount recognised must not exceed the provision.

Specific applications

Restructuring provisions may be recognised only where a detailed formal plan exists identifying the business or part concerned, the principal locations affected, the location, function and approximate number of employees to be compensated, the expenditure to be undertaken, and when the plan will be implemented; and where a valid expectation has been raised in those affected, either by starting to implement the plan or by announcing its main features to them.

A restructuring provision includes only direct expenditures necessarily entailed by the restructuring and not associated with the ongoing activities. It excludes retraining or relocating continuing staff, marketing, and investment in new systems and distribution networks.

Onerous contracts — where the unavoidable costs of meeting the obligations exceed the economic benefits expected to be received — require the present obligation under the contract to be recognised as a provision.

Future operating losses are not provided for, because they do not arise from a past event and there is no present obligation.

AS 15 — Employee Benefits

The four categories

Short-term employee benefits fall due wholly within twelve months after the end of the period in which employees render the service — wages, salaries, paid annual and sick leave, profit-sharing and bonuses payable within twelve months, and non-monetary benefits. They are recognised as an undiscounted amount in the period in which the service is rendered.

Post-employment benefits are payable after employment ends — gratuity, pension, post-employment medical care. Their accounting depends entirely on a classification.

Other long-term employee benefits include long-service leave, sabbaticals, jubilee benefits, and long-term disability benefits.

Termination benefits arise from an enterprise's decision to terminate employment before normal retirement date, or an employee's decision to accept voluntary redundancy. They are recognised as a liability and expense when, and only when, the enterprise is demonstrably committed either to terminate the employment of an employee or group before the normal retirement date, or to provide termination benefits as a result of an offer made to encourage voluntary redundancy.

The classification that decides everything

Defined contribution plans are post-employment benefit plans under which the enterprise pays fixed contributions into a separate entity and has no legal or constructive obligation to pay further contributions if the fund does not hold sufficient assets. The actuarial risk and the investment risk fall on the employee. The accounting is simple: the contribution payable for the period is recognised as an expense.

Defined benefit plans are all other post-employment plans. The enterprise's obligation is to provide the agreed benefits, and the actuarial risk and investment risk fall on the enterprise. The accounting is correspondingly complex: the obligation is measured on an actuarial basis using the projected unit credit method, plan assets are measured at fair value, and the net figure is recognised.

Gratuity in India is characteristically a defined benefit obligation, because the employer promises a formula-determined amount regardless of what any fund has earned.

AS 7 — Construction Contracts

Why it exists

A contract that spans three financial years poses a problem no other revenue standard has to solve. If revenue were recognised only on completion, two years would show nothing and the third would show everything, which describes neither year truthfully.

AS 7 requires the percentage of completion method. Contract revenue and contract costs are recognised as revenue and expenses respectively by reference to the stage of completion of the contract activity at the balance sheet date, when the outcome of a construction contract can be estimated reliably.

Note what is not there: AS 7 permits no completed contract method. That option existed under the earlier standard and does not survive.

When the outcome can be estimated reliably

For a fixed price contract, all four of the following must hold: total contract revenue can be measured reliably; it is probable that the economic benefits will flow to the enterprise; both the contract costs to complete and the stage of completion at the balance sheet date can be measured reliably; and the contract costs attributable to the contract can be clearly identified and measured reliably so that actual costs can be compared with prior estimates.

For a cost plus contract, two conditions: it is probable that the economic benefits will flow, and the contract costs attributable to the contract, whether or not specifically reimbursable, can be clearly identified and measured reliably.

When it cannot

Where the outcome cannot be estimated reliably, revenue is recognised only to the extent of contract costs incurred of which recovery is probable, and contract costs are recognised as an expense in the period incurred. No profit is recognised.

The rule that overrides everything

When it is probable that total contract costs will exceed total contract revenue, the expected loss is recognised as an expense immediately, regardless of the stage of completion, regardless of whether work has commenced, and regardless of the outcome of other contracts. This is prudence applied to contracts, and it is the most commonly examined single point in AS 7.

Stage of completion

May be determined by the proportion that contract costs incurred for work performed to date bear to the estimated total contract costs, by surveys of work performed, or by completion of a physical proportion of the contract work. Progress payments and advances received from customers do not necessarily reflect the work performed and are not a basis for measuring the stage of completion.

AS 9 — Revenue Recognition

Scope

AS 9 deals with revenue arising from the sale of goods, the rendering of services, and the use by others of enterprise resources yielding interest, royalties and dividends. It expressly excludes revenue from construction contracts, hire purchase and lease agreements, government grants, and insurance contracts of insurance companies.

Revenue is the gross inflow of cash, receivables or other consideration arising in the course of ordinary activities. It excludes amounts collected on behalf of third parties.

Sale of goods

Revenue is recognised when the seller has transferred to the buyer the property in the goods for a price, or all significant risks and rewards of ownership have been transferred and the seller retains no effective control of the goods to a degree usually associated with ownership; and no significant uncertainty exists regarding the amount of consideration.

Where significant uncertainty exists as to ultimate collection, revenue recognition is postponed. Where the uncertainty arises subsequently, after revenue has already been recognised, the provision is made against the receivable and revenue is not reversed — a distinction that is examined.

Rendering of services

Recognised by the completed service contract method or the proportionate completion method, according to which relates the revenue to the work accomplished.

Interest, royalties and dividends

Interest accrues on a time proportion basis, taking into account the amount outstanding and the rate applicable. Royalties accrue in accordance with the terms of the relevant agreement. Dividends are recognised when the right to receive payment is established.

AS 4 — Contingencies and Events Occurring After the Balance Sheet Date

The heart of this standard is a distinction that is easy to state and constantly misapplied.

Adjusting events provide additional evidence of conditions that existed at the balance sheet date. The figures are adjusted. The insolvency of a customer that was already in difficulty, confirming that a receivable was not recoverable at the year end; the settlement of a court case confirming a present obligation at the year end; the discovery of fraud or errors showing the statements were incorrect.

Non-adjusting events arise from conditions that arose after the balance sheet date. The figures are not adjusted, but disclosure is required where the event is of such significance that non-disclosure would affect the ability of users to make proper evaluations. A fire destroying a factory two weeks after the year end; a major acquisition; a decline in market value of investments after the year end.

Two specific rules must be known. Proposed dividends declared after the balance sheet date but relating to the period are not recognised as a liability at the balance sheet date; they are disclosed. And an event occurring after the balance sheet date that indicates the going concern assumption is no longer appropriate requires a fundamental change in the basis of accounting, regardless of whether it would otherwise be an adjusting event.

AS 5 — Net Profit or Loss for the Period, Prior Period Items and Changes in Accounting Policies

Ordinary activities are activities undertaken as part of the business and related activities that the enterprise undertakes in furtherance of, incidental to, or arising from these activities.

Extraordinary items are income or expenses that arise from events or transactions clearly distinct from the ordinary activities and therefore not expected to recur frequently or regularly. They are disclosed separately as part of net profit or loss for the period, with their nature and amount stated.

Prior period items are income or expenses which arise in the current period as a result of errors or omissions in the preparation of the financial statements of one or more prior periods. The word errors is load-bearing: a revision of an estimate is not a prior period item, however large. Prior period items are separately disclosed so that their impact on the current profit or loss can be perceived.

Change in accounting policy is made only if required by statute, for compliance with an accounting standard, or if it is considered that the change would result in a more appropriate presentation. The amount by which any item is affected must be disclosed to the extent ascertainable; where not ascertainable, that fact must be stated.

Change in accounting estimate is applied prospectively, in the period of change if it affects only that period, or in the period of change and future periods if it affects both. The nature and amount of a change having a material effect is disclosed.

Where it is difficult to distinguish a change in policy from a change in estimate, the change is treated as a change in estimate, with appropriate disclosure.

AS 11 — The Effects of Changes in Foreign Exchange Rates

Initial recognition: a foreign currency transaction is recorded by applying the exchange rate at the date of the transaction.

At each balance sheet date:

  • Monetary items — money held and items to be received or paid in fixed or determinable amounts of money — are reported using the closing rate.
  • Non-monetary items carried at historical cost are reported using the exchange rate at the date of the transaction, so they do not move.
  • Non-monetary items carried at fair value are reported using the rates that existed when the values were determined.

Exchange differences arising on the settlement of monetary items or on reporting them at rates different from those at which they were initially recorded are recognised as income or expense in the period in which they arise.

Forward exchange contracts not intended for trading or speculation: the premium or discount, being the difference between the forward rate and the spot rate at inception, is amortised as expense or income over the life of the contract. Exchange differences on such a contract are recognised in profit for the period. For a contract intended for trading or speculation, the gain or loss is computed by the difference between the forward rate available at the reporting date for the remaining maturity and the contracted rate, and is recognised in profit.

Foreign operations are classified as integral — carried on as though an extension of the reporting enterprise's operations — or non-integral. Integral operations are translated as if the transactions were those of the reporting enterprise itself. For non-integral operations, assets and liabilities are translated at the closing rate, income and expense items at the rates at the dates of the transactions, and the resulting exchange difference is accumulated in a foreign currency translation reserve until disposal of the net investment.

AS 12 — Government Grants

Grants related to specific fixed assets may be presented either by deducting the grant from the gross value of the asset, or by treating it as deferred income which is recognised in profit and loss on a systematic and rational basis over the useful life of the asset. Where a grant equals the whole or virtually the whole cost of an asset, the asset is shown at a nominal value.

Grants related to revenue are presented either as a credit in the profit and loss statement or as a deduction from the related expense.

Grants of the nature of promoters' contribution — where no repayment is ordinarily expected and the grant is given as a contribution towards total capital outlay — are credited to capital reserve and treated as part of shareholders' funds.

Non-monetary grants given at a concessional rate are accounted for at their acquisition cost; where given free of cost, at a nominal value.

Refund of a grant is treated as an extraordinary item. A grant related to revenue is applied first against any unamortised deferred credit, and any excess is charged to profit. For a grant related to a fixed asset, the carrying amount is increased or the deferred income balance reduced by the amount refundable, and the resulting additional depreciation is recognised prospectively.

AS 14 — Accounting for Amalgamations

The classification is developed fully in the amalgamation chapter; what belongs here is the definitional core.

Amalgamation in the nature of merger requires all five conditions: all assets and liabilities of the transferor become those of the transferee; shareholders holding not less than ninety per cent of the face value of the equity shares of the transferor become equity shareholders of the transferee; the consideration for those shareholders is discharged wholly by the issue of equity shares, except for cash in respect of fractional shares; the business of the transferor is intended to be carried on by the transferee; and no adjustment is intended to the book values of the assets and liabilities except to ensure uniformity of accounting policies.

Failing any one condition makes it an amalgamation in the nature of purchase. The pooling of interests method applies to a merger; the purchase method applies to a purchase.

AS 22 — Accounting for Taxes on Income

The problem

Taxable income and accounting profit differ, because tax law and accounting standards answer different questions. If tax expense in the accounts were simply the tax payable for the year, the tax charge would not correspond to the profit reported alongside it, and the matching principle would be broken.

AS 22 solves this by recognising deferred tax on timing differences.

Permanent differences originate in one period and do not reverse — a disallowed expense that will never be allowed. They create no deferred tax.

Timing differences originate in one period and are capable of reversal in one or more subsequent periods — depreciation charged at different rates for accounting and tax, expenses allowed on payment rather than accrual. These create deferred tax.

Recognition

Deferred tax liabilities are recognised for all timing differences, subject to the considerations of prudence.

Deferred tax assets are recognised and carried forward only to the extent that there is a reasonable certainty that sufficient future taxable income will be available against which they can be realised.

Where there are unabsorbed depreciation or carry forward of losses under tax laws, the test is stricter: deferred tax assets are recognised only to the extent that there is virtual certainty supported by convincing evidence that sufficient future taxable income will be available.

Deferred tax is measured using the tax rates and tax laws that have been enacted or substantively enacted by the balance sheet date. Deferred tax assets and liabilities are not discounted.

The carrying amount of deferred tax assets is reviewed at each balance sheet date and written down to the extent it is no longer reasonably certain, or virtually certain as the case may be, that sufficient future taxable income will be available.

Key formulas & results

Everything to memorise for the exam hall, in one card. Screenshot this for revision.

Provision recognised only if ALL of: present obligation from a past event, probable outflow, reliable estimate
Possible obligation or possible outflow = contingent liability, disclosed not recognised; remote = neither
Expected value measurement = sum of (each possible outcome x its probability), used for a large population of items
AS 7 stage of completion = contract costs incurred for work performed to date / estimated total contract costs
AS 7 expected loss = total contract costs expected to exceed total contract revenue, recognised in full immediately regardless of stage
AS 7 where outcome not reliably estimable: revenue = contract costs incurred that are probably recoverable; no profit
AS 11 closing rate for monetary items; transaction-date rate for non-monetary items at historical cost
AS 11 forward contract premium or discount = forward rate less spot rate at inception, amortised over the contract life
Deferred tax = timing difference x tax rate enacted or substantively enacted at the balance sheet date, undiscounted
Deferred tax asset on unabsorbed depreciation or carried forward losses requires virtual certainty supported by convincing evidence; otherwise reasonable certainty
⚠️

Traps CA Intermediate sets — and how to dodge them

These are the exact option-traps and misreads that cost marks under negative marking.

WATCH OUT
Recognising a provision for future operating losses, which arise from no past event and create no present obligation
WATCH OUT
Providing for a restructuring on a board decision alone, without a detailed formal plan and a valid expectation raised in those affected
WATCH OUT
Netting an expected reimbursement against a provision instead of recognising it as a separate asset, and recognising it before it is virtually certain
WATCH OUT
Discounting a provision under AS 29, which the Indian standard does not permit
WATCH OUT
Disclosing a contingent asset; AS 29 requires no disclosure at all until the inflow is virtually certain
WATCH OUT
Deferring an expected loss on a construction contract until the loss-making stage is reached, instead of recognising it in full immediately
WATCH OUT
Using progress payments or advances received as the measure of the stage of completion
WATCH OUT
Reversing revenue when collection becomes doubtful after recognition; the correct treatment is a provision against the receivable
WATCH OUT
Recognising a proposed dividend declared after the balance sheet date as a liability at that date
WATCH OUT
Treating a large revision of an estimate as a prior period item; prior period items arise only from errors or omissions
WATCH OUT
Translating non-monetary items carried at historical cost at the closing rate
WATCH OUT
Creating deferred tax on a permanent difference, which by definition never reverses
WATCH OUT
Recognising a deferred tax asset on carried forward losses on the reasonable certainty test rather than the stricter virtual certainty test

Exam-pattern practice

PYQ-style questions with full solutions. Work through them as a readiness check — mark yourself honestly and get your gap report at the end.

Readiness check

Are you exam-ready for Liability, Revenue and Impact Standards?

15 problems from this chapter. Try each one, reveal the worked solution, mark yourself honestly — get your gap report at the end.

15 questions~11 min

5-minute revision

The whole chapter, distilled. Read this the night before the exam.

  • AS 29 three-step test: present obligation from a past event, probable outflow, reliable estimate — all three or no provision
  • Possible = contingent liability disclosed; remote = nothing; contingent asset = neither recognised nor disclosed
  • A board decision creates no obligation until communicated to those affected so as to raise a valid expectation
  • Future operating losses are never provided for; onerous contracts are
  • AS 29 provisions are not discounted, and reimbursements are a separate asset recognised only when virtually certain
  • AS 15: defined contribution puts actuarial and investment risk on the employee; defined benefit puts both on the enterprise
  • AS 7 permits only percentage of completion; an expected loss is recognised in full immediately whatever the stage
  • Progress payments never measure the stage of completion
  • AS 9: uncertainty before recognition postpones revenue; uncertainty after recognition creates a provision without reversing revenue
  • AS 4: adjusting events evidence conditions existing at the balance sheet date; proposed dividends are disclosed, not recognised
  • AS 5: prior period items arise from errors or omissions only; a revised estimate is never one, however large
  • AS 11: monetary items at closing rate; non-monetary items at historical cost stay at the transaction-date rate
  • AS 12: asset grants either deducted from cost or held as deferred income, both giving the same profit effect; promoters' contribution goes to capital reserve
  • AS 22: only timing differences create deferred tax; permanent differences never do
  • Deferred tax assets need reasonable certainty, but virtual certainty supported by convincing evidence where there is unabsorbed depreciation or carried forward loss

CA Intermediate question blueprint

How this topic is asked, tier by tier — so you can prep to the pattern.

Typical weightage: 14

Exam-hall strategy

Battle-tested tips from mentors and toppers for this topic under the sectional clock.

  1. For any AS 29 question, walk the decision tree explicitly in writing — present obligation, probability of outflow, reliability of estimate — before stating a conclusion
  2. Say whether an obligation is legal or constructive; the mark is often for identifying a constructive obligation where no contract exists
  3. In AS 7 problems, compute total expected cost against total contract revenue first, because if a loss is expected that rule overrides everything else you were about to do
  4. In AS 4 questions, state for each event whether the condition existed at the balance sheet date; that sentence is the reasoning and carries the mark
  5. In AS 11 problems, label each item monetary or non-monetary before translating anything
  6. In AS 22 problems, separate permanent from timing differences in a short table before computing, and reconcile total tax expense to the adjusted accounting profit as a check
  7. Name the stricter virtual certainty test whenever unabsorbed depreciation or carried forward losses appear; using reasonable certainty there is a guaranteed lost mark

Beyond the exam

Where this skill shows up in the job you're competing for — and in life.

Warranty and litigation provisions are among the most jud…

Warranty and litigation provisions are among the most judgemental figures in any set of accounts, and the three-step AS 29 test is exactly what an audit team documents when challenging them

The AS 7 expected loss rule is why a contractor's profit …

The AS 7 expected loss rule is why a contractor's profit warning often comes long before the loss-making contract is finished

Deferred tax is the reason a company's effective tax rate…

Deferred tax is the reason a company's effective tax rate differs from the statutory rate, and reconciling the two is a standard analyst exercise

AS 4's adjusting and non-adjusting distinction governs wh…

AS 4's adjusting and non-adjusting distinction governs what a company must do about news arriving between its year end and the signing of its accounts, which is a live question at every audit closing meeting

Where else this topic is tested

Prepare once, score in every exam that asks it.

CA Final Paper 1 — Financial Reporting, where Ind AS 37, 19, 115, 10, 8, 21, 20 and 12 extend this material
CMA Intermediate — Financial Accounting and Corporate Accounting
CS Executive — Corporate and Management Accounting
ACCA Financial Reporting, where provisions, construction contracts and deferred tax are examined in the same form

Questions aspirants ask

Pulled from the Q&A community and mentor sessions.

Because the two errors have different consequences for the reader. Understating an obligation misleads a creditor into extending credit that will not be repaid; overstating a possible gain misleads an investor into paying for income that may never arrive. AS 29 resolves the asymmetry by disclosing possible losses and saying nothing about possible gains, on the view that a reader who is surprised by good news is better served than one surprised by bad. The practical corollary is that once an inflow becomes virtually certain the item is no longer a contingent asset at all, and is recognised as an ordinary asset.

A liability is an obligation whose amount is known or determinable. A provision is a liability which can be measured only by using a substantial degree of estimation, so it is a liability of uncertain timing or amount rather than something less than a liability — a distinction candidates often get backwards. A reserve is not a liability at all: it is an appropriation of profit, part of shareholders' funds, created by a decision about how to label retained earnings rather than by any obligation to an outsider. The practical test is whether an external party can compel payment. A provision for warranty means customers can require repairs; a general reserve means nobody can require anything.

No, and this is a change from the earlier position that older material still reflects. AS 7 as it now stands requires the percentage of completion method where the outcome of a construction contract can be estimated reliably. Where the outcome cannot be reliably estimated, the treatment is not the completed contract method either: revenue is recognised only to the extent of contract costs incurred of which recovery is probable, and contract costs are expensed as incurred, so no profit is recognised but revenue and costs still flow through each period. If a book offers you a choice between percentage of completion and completed contract, it is describing the superseded standard.

Ask whether the item will ever be allowed or taxed in some other year. If yes, it is timing; if never, it is permanent. Depreciation charged at different rates in the books and under tax law is timing, because the total allowed over the asset's life is the same and only the pattern differs. An expense allowed only on payment is timing, because payment will eventually come. A disallowed donation or a penalty is permanent, because no year will ever allow it. Exempt income is permanent for the same reason in the other direction. Only timing differences generate deferred tax, since deferred tax exists precisely to account for a reversal that is going to happen.

The classification and its consequences are heavily examinable; the actuarial mechanics much less so. You must be able to distinguish a defined contribution from a defined benefit plan, say who bears actuarial and investment risk under each, state the four categories of employee benefit, and explain when termination benefits are recognised. You should know that a defined benefit obligation is measured using the projected unit credit method and that plan assets are measured at fair value. Full actuarial computations belong to CA Final. Where a numerical question appears at Intermediate it is usually a defined contribution charge or a straightforward short-term benefit accrual.